8/11/2026

Sealed · verified

Partly cloudy · 19–31°C

Labor

Bricklayer6 person(s)8h
Labourer4 person(s)8h
Site foreman1 person(s)8h

Incidents2

Delay / stoppage

Concrete arrived 1h40 late after a batching plant breakdown. Crew idle for that period.

Site visit / inspection

Client visit at 15:00 to inspect the slab.

Equipment on site

Tower crane, concrete mixer truck, poker vibrator

Notes

Level 2 slab pour completed. Formwork to level 3 started at the west end.

Photos0

No photos.