Partly cloudy · 19–31°C
| Bricklayer | 6 person(s) | 8h |
| Labourer | 4 person(s) | 8h |
| Site foreman | 1 person(s) | 8h |
Concrete arrived 1h40 late after a batching plant breakdown. Crew idle for that period.
Client visit at 15:00 to inspect the slab.
Tower crane, concrete mixer truck, poker vibrator
Level 2 slab pour completed. Formwork to level 3 started at the west end.
No photos.
✓ Log sealed
Sealed on 8/11/26, 6:12 PM
SHA-256
8827a3b38c6f5236da1f1408516f01bb617174638215dc0687509c8bbfdfdc8e