Clear · 20–33°C
| Steel fixer | 5 person(s) | 8h |
| Labourer | 3 person(s) | 8h |
| Site foreman | 1 person(s) | 8h |
Additional reinforcement instructed by the supervising engineer at columns P12-P14.
Tower crane, bar cutting and bending machine
Level 2 slab reinforcement fixed and checked. Ready for the pour tomorrow.
No photos.
✓ Log sealed
Sealed on 8/10/26, 5:48 PM