Partly cloudy · 19–31°C
| Bricklayer | 6 شخص | 8h |
| Labourer | 4 شخص | 8h |
| Site foreman | 1 شخص | 8h |
Concrete arrived 1h40 late after a batching plant breakdown. Crew idle for that period.
Client visit at 15:00 to inspect the slab.
Tower crane, concrete mixer truck, poker vibrator
Level 2 slab pour completed. Formwork to level 3 started at the west end.